Frazier’s Concrete Division erects 65,000 facility
| 12 Sep 2012 |
At the Tactical Equipment Maintenance Facility in Fort Hunter Liggett, CA, Frazier’s Concrete Division safely erected a 65,000 SF, 50-panel, accelerated schedule project with just 6 weeks from ground breaking to completing panel erection. The tallest panel was 42’ and the heaviest 170,000 lbs. View highlights of the building erection process here. |
|
 |
Frazier Masonry was timely, professional and cost-effective. Thank you for being a part of this project. I look forward to working with you again in the future.