Frazier places 55,000 block per week at USMC BEQ Package 5
| 09 Sep 2010 |
Frazier Masonry is providing Structural CMU services for the USMC BEQ Package 5 project at MCB Camp Pendleton, CA. On average Frazier is placing 55,000 block per week on this job. Frazier is proud to partner with San Diego based Harper Construction on this project. View the latest jobsite images by clicking here. |
|
 |
Frazier's performance has exceeded our expectations by meeting our tight schedule, delivering a quality product, and coordinating their work with other trades and interferences. We are hoping to continue our successful relationship with Frazier Masonry and hope to see them on our next project.

- Frank E. Smith - Senior Project Manager - ET Environmental
|
|
|