LACDPW - Fire Station #136 - Palmdale, CA



San Fernando Regional Swimming Pool
Frazier Masonry crews completed 24 CMU buildings in six and half months as part of a Soltek Pacific design build project. Frazier Masonry overcame sand storms, extreme winds and even a blanket of snow. Transportation challenges, lack of onsite water reserves and no utilities did not stop production. [They] exceeded expectations by completing the project 17 days ahead of the baseline schedule. As a Project Superintendent I look forward to working with Frazier Masonry in the future.
--Joe Whipple - Project Superintendent - Soltek Pacific Construction