Frazier Concrete pours 65,000 SF of slab-on-grade in 20 hours
| 14 Aug 2013 |
Frazier placed 65,000 SF or 1331 CYDS of concrete overnight in a single pour while utilizing two telebelts and two laser screeds at the Fedex Ground facility in Henderson, NV. It took only 20 hours from start of placement to completion of saw-cutting & curing. The project called for staffing 3 rotation shifts comprised of twenty five workers and received a remarkable floor flatness evaluation of 50/44 FF/FL. View slideshow here. |
|
 |
Frazier's performance has exceeded our expectations by meeting our tight schedule, delivering a quality product, and coordinating their work with other trades and interferences. We are hoping to continue our successful relationship with Frazier Masonry and hope to see them on our next project.

- Frank E. Smith - Senior Project Manager - ET Environmental
|
|
|