Frazier Concrete completes 300,000 SF FedEx facility in 9 weeks

31 Oct 2013

At the FedEx Ground facility in Henderson, NV, Frazier Concrete safely erected 150 individual tilt up panels in just four 8-hour days. Frazier placed 300,000 SF of slab-on-grade in just 8 placements, with the largest being 65,000 SF in a single pour. From foundation layout to panel erection, the FedEx facility was completed in record time, only 9 weeks. View project slideshow here.


Sparks Crossing - Sparks, NV
Frazier provided the high-end quality results and timeliness required to keep this job on schedule. This is a group of talented individuals who work exceedingly well as a team; with a well served "whatever it takes" attitude.
- Pudge Linman - Director of Construction - Westin Verasa Residences