Frazier Concrete completes 300,000 SF FedEx facility in 9 weeks
| 31 Oct 2013 |
At the FedEx Ground facility in Henderson, NV, Frazier Concrete safely erected 150 individual tilt up panels in just four 8-hour days. Frazier placed 300,000 SF of slab-on-grade in just 8 placements, with the largest being 65,000 SF in a single pour. From foundation layout to panel erection, the FedEx facility was completed in record time, only 9 weeks. View project slideshow here. |
|
 |
Frazier's performance has exceeded our expectations by meeting our tight schedule, delivering a quality product, and coordinating their work with other trades and interferences. We are hoping to continue our successful relationship with Frazier Masonry and hope to see them on our next project.