Frazier Concrete completes 300,000 SF FedEx facility in 9 weeks

31 Oct 2013

At the FedEx Ground facility in Henderson, NV, Frazier Concrete safely erected 150 individual tilt up panels in just four 8-hour days. Frazier placed 300,000 SF of slab-on-grade in just 8 placements, with the largest being 65,000 SF in a single pour. From foundation layout to panel erection, the FedEx facility was completed in record time, only 9 weeks. View project slideshow here.


Winco #103 - Tracy, CA
Frazier went above and beyond expectations in driving the project schedule and completing each phase before its due date. We were very pleased to have Frazier on board as our concrete subcontractor for this Project, and will definitely use their services again.
- Marlon Gahring - Project Superintendent - ET Environmental