Frazier Concrete completes 300,000 SF FedEx facility in 9 weeks
| 31 Oct 2013 |
At the FedEx Ground facility in Henderson, NV, Frazier Concrete safely erected 150 individual tilt up panels in just four 8-hour days. Frazier placed 300,000 SF of slab-on-grade in just 8 placements, with the largest being 65,000 SF in a single pour. From foundation layout to panel erection, the FedEx facility was completed in record time, only 9 weeks. View project slideshow here. |
|
 |
Thanks again for all of your efforts. It makes me proud to see we still have Masons that still take pride in their work!

- Dennis McCown - CQC Manager - Soltek Pacific Construction
|
|
|