Frazier’s Concrete Division erects 56 tilt-up panels in 11 hours
| 30 Nov 2011 |
At the NW Satellite Transport Facility in North Las Vegas, Frazier’s Concrete Division safely erected the 41,000 SF, 56-panel, main building facility in 11 eleven hours flat. The 44,500 SF project consists of the main building, bus wash, generator enclosure and trash enclosure with a total of 81 tilt-up panels, the tallest panel being 33’-1”, the heaviest 80,000 lbs. View images of the building erection process here. |
|
 |
A company is only as good as the people in the field and in this case Frazier Masonry should be proud. The quality of Frazier\s work is off the charts, in addition to their timeliness and adherence to the schedule. I look forward to working with Frazier in the future.

- Russell Trozera - Site Manager - Osborn Construction Management
|
|
|