Frazier’s Concrete Division erects 56 tilt-up panels in 11 hours | 30 Nov 2011 |
At the NW Satellite Transport Facility in North Las Vegas, Frazier’s Concrete Division safely erected the 41,000 SF, 56-panel, main building facility in 11 eleven hours flat. The 44,500 SF project consists of the main building, bus wash, generator enclosure and trash enclosure with a total of 81 tilt-up panels, the tallest panel being 33’-1”, the heaviest 80,000 lbs. View images of the building erection process here. |
|
|
The "can do" attitude and the ability to make and meet commitments by every one of your team contributed greatly toward making this a successful project. We look forward to the opportunity to work together in the future.
- David Yung - Ledcor Construction Inc.
|
|
|