Frazier’s Concrete Division erects 56 tilt-up panels in 11 hours

30 Nov 2011

At the NW Satellite Transport Facility in North Las Vegas, Frazier’s Concrete Division safely erected the 41,000 SF, 56-panel, main building facility in 11 eleven hours flat. The 44,500 SF project consists of the main building, bus wash, generator enclosure and trash enclosure with a total of 81 tilt-up panels, the tallest panel being 33’-1”, the heaviest 80,000 lbs. View images of the building erection process here.